Navigation:  Menu Commands > Edit Menu >

Baseline Shift command (Edit menu)

JR   Viewer

Print this Topic Previous pageReturn to chapter overviewNext page

Allows you to specify a new value at a specific time in a record generated from the primary data file in "data processing" mode.

If the Constant Baseline Shift checkbox is checked, then the shift is applied to all points in the primary record. Otherwise, you may specify a start time and end time.

The start time must be less than the time at which you want the integrated record to match the value you specify.

After altering the primary record, DPlot will automatically regenerate integrated records and, if the shift is applied to all points, will update the CBS display in the title.

DPlot maintains a list of all shifts applied to the primary record, which can be displayed with the List Editions command.

____________________________

See also

 Data Processing

 

 


Page url: https://www.dplot.com/help/index.htm?helpid_baselineshift.htm